Northampton General Hospital Accelerator Building (LINAC)
Client:
Northampton General Hospital NHS Trust
Contract:
JCT1998 with Contractors Design
The first bunker was handed over 6 months before the remainder of the building, so that the specialist medical equipment could be installed, commissioned and staff trained, ready for use when the building was completed.