STEPNELL Building and Civil Engineering

01788 574 511
info@stepnell.co.uk

Northampton General Hospital Accelerator Building

Case Study - NHG Combined Case (1) 200

Client:
Northampton General Hospital
Value:
£8,870,000
Contract:
JCT1998 with Contractors Design
Duration:
66 Weeks
Category:
Health Care

Case Study - NHG Combined Case (2) 200

A four storey steel framed building, linking in to existing adjacent hospital buildings in six different locations.  Each floor housing a different medical specialty., including cardiac treatment centre, renal treatment ward, nuclear medicine department and Radiopharmacy clean room suite.

Case Study - NHG Combined Case (4) 200

An extremely restricted site, new building surrounded by existing on 3 sides and actually built over existing live hospital buildings in 3 separate locations. Worked closely with client’s medical teams to incorporate specialist medical equipment within the design as it was selected.  Refurbished adjacent live hospital restaurant during the project and installed a new electrical substation to provide power for the new building.